50MW Adani Phuoc Minh Photovoltaic Project in Vietnam
50MW Adani Phuoc Minh Photovoltaic Project in Vietnam is located in Ninh Thuan Province, Vietnam, which belongs to the central and southern coastal areas of Vietnam. The total installed capacity of the project reaches 50MWp and covers an area of approximately 59.86 hectares. The EPC construction service includes centralized PV Plant, 110kV booster stations and transmission line projects.
(Electrical engineering design drawing)
(110kV booster station)
The photovoltaic modules use DC1500 system monocrystalline silicon 450Wp, and 28 monocrystalline silicon modules form a string.
The bracket adopts a flat single-axis tracking bracket. Equipped with 221 string inverters with an inverter capacity of 175kW. A total of seven 5700kVA box transformers are installed on the distribution side, and the high-voltage side voltage is 22kV.
(Distribution room)
The cables are laid underground and collected into the 22kV power distribution room of the booster station through three collection lines. Build a new 110kV booster station and 110kV transmission line.
(Equipment within the booster station)
During the construction period, due to the impact of the pandemic, personnel from various parties involved in the project were unable to enter Vietnam and were stranded in third countries, completing preliminary work separately in different regions.
(Online meeting)
The project officially commenced on June 19th, and within a mere 90 days post-commencement, both the booster station and the line construction were completed, enabling commercial operation. Despite the challenges posed by the pandemic, the project not only achieved the COD target two months ahead of schedule but also showcased the project team's capability to accomplish the seemingly impossible tasks, setting yet another speed record in the solar photovoltaic construction cycle.
(Installation of project pile foundations and brackets)
(Pile construction for the project)
(Installation of tracking support brackets)
(Grid-feeding)
As a result, this project stood out among other solar projects under construction in Ninh Thuan province, entering the high tariff range of the province's 2GW "first built, first served" policy. It successfully assisted the owner in locking in the optimal tariff and received high recognition from the owner.
(Project kickoff meeting)
(Project team group photo after achieving COD)