Successful Grid Connection of 100MWp HCG, HTG Photovoltaic Project in Vietnam

2024.04.12 Share:

The HCG and HTG photovoltaic turnkey project in Tinh Tay Ning, Vietnam, achieved full capacity grid connection and commenced power generation on May 26,2019. The COD certificate was obtained on June 7, 2019, marking the early achievement of significant milestones outlined in the EPC contract. With this, the project officially entered commercial operation.


(The HCG&HTG project)


The project is situated within the province of Tinh Tay Nin, bordering Cambodia to the west. It comprises a 117-hectare photovoltaic field, a 110KV substation, and a 7-kilometer transmission line, with a total capacity of 100MWp.



The project was contracted at the end of September 2018, and construction officially commenced on October 20th of the same year. With a total installed capacity of 2×50MWp, both the HCG and HTG blocks were constructed simultaneously, sharing a single booster station.


(Project Commencement Ceremony)


Since the official commencement of construction on October 20, 2018, the project team has been keenly aware of the project's broad scope and tight schedule. With ensuring the timeline as the core objective, they meticulously planned the implementation of key and challenging aspects of the project.


(Living area)


(On-site piling)


They made innovative attempts in collaborating with local design institutes to optimize the procurement process of equipment and materials. They also achieved significant breakthroughs in the construction management of the booster station and the 110kV transmission line. Moreover, they successfully optimized and innovated a construction plan using grouted anchors to connect precast solid concrete piles with brackets, effectively advancing the project schedule.


(Booster station)


In an extremely short time frame, they achieved the implementation of design, funding, pile supply, major equipment procurement, mobilization of construction equipment, and organization of construction personnel. They strengthened management, prioritized safety, and rigorously controlled quality and progress during project implementation. With the support of PowerChina International Regional Headquarters and the collective efforts of all participating parties, they ultimately achieved the significant milestone of completing the COD of the project ahead of schedule.