74.1MW Philippines Nexif CARE PV Power Station
- 项目名称
- 74.1MW Philippines Nexif CARE PV Power Station
- 项目地址
- Calabanga Province, Southern Luzon
- 项目类型
- Centralized Photovoltaic Project
- 并网时间
- 2024
- 总装机容量
- 74.1MW
On April 17, 2024, the 74.1MW Nexif CARE photovoltaic power station in the Philippines was successfully connected to the grid for power generation. The project started on June 16, 2023. The project is located in Calabanga Province, Southern Luzon, Philippines. The project investor is Calabanga Renewable Energy Co., Ltd., and the EPC general contractor is Huadong Engineering Corporation Limited.
Sinohydro Foundation Engineering Co., Ltd. is mainly responsible for the construction of temporary construction, site leveling, photovoltaic field piles, brackets, components, collection lines, roads, drainage, and other construction work, as well as the construction and decoration of the 69 kV booster station and other civil engineering and installation work.